Operational and Maintenance Costs: All Three Bridges

Date: 07/01/09

Kittery/Portsmouth Bridge Costs by Fiscal Year

Memorial Bridge Operational and Maintenance Costs

YEAR    OP. COST       MAINT. COST        TOTAL COST
               
2008    $996,321.81     $75,122.36             $1,071,444.17   
2007    $865,911.75   $122,163.89                $988,075.64   
2006    $835,386.38     $85,428.55                $920,814.93   
2005    $769,239.44     $56,985.50                $826,224.94   
2004    $679,368.11     $50,099.24                $729,467.35   
2003    $599,767.77     $59,348.37                $659,116.14                   
               
- These are actual costs incurred--taken from invoices.     

- Operating Costs include Labor, Benefits, Telephone, Vehicle Usage and Upkeep,
Electricity, and Propane           

- Maintenance Costs include Labor, Benefits, Materials, Repair Contracts, Vehicle Usage and Upkeep, Equipment Rental and Delivery Charges        
               
               
Sarah Long Bridge Operational and Maintenance Costs
                   
YEAR    OP. COST      MAINT. COST  RAIL COST        TOTAL
                   
2008    $692,049.19    $281,714.54    $48,210.63     $1,021,974.36   
2007    $603,027.36    $269,387.70    $11,896.03         $884,311.09   
2006    $598,864.23    $263,090.48    $12,329.18        $874,283.89   
2005    $469,833.08    $210,884.96    $25,073.26        $705,791.30   
2004    $439,210.19    $213,350.45    $13,787.17        $666,347.81   
2003    $384,367.77    $126,749.15      $9,880.60        $520,997.52   
                   
*Operating Costs include Labor, Benefits, Telephone, Vehicle Usage and Upkeep, Electricity, and Propane           
                   
* Maintenance Costs include Labor, Benefits, Materials, Repair Contracts, Vehicle Usage and Upkeep, Equipment Rental and Delivery Charges            
                   
* Railroad Costs include Labor, Benefits, Vehicle Usage and Upkeep, Electricity, Equipment Rental
    and Materials.                
                            
Additional Sarah Long Expenditures:   
       
* FY 08   Project 99896D  Permanent Electrical Repairs Cost:  $1.6 Million     
* FY 08   Project 14789  Emergency Electrical Repairs Cost:  $805,317       
                   

High Level Bridge Operational and Maintenance Costs

FY,               99890                99891              99892            TOT. COST
2008        $4,347.00         $60,844.14        $4,805.32         $69,996.46
2007               $0.00         $36,668.31        $5,723.86         $42,392.17
2006      $24,936.00         $63,628.74        $8,636.65         $97,201.39
2005           $596.00         $57,946.42      $28,017.05         $86,559.47
2004        $6,930.00         $48,107.82        $3,579.29         $58,617.11
2003        $4,696.00         $76,066.91        $1,999.31         $82,762.22

               
 - 99890 includes all maintenance on the southerly abutment and approach spans in New Hampshire up to but excluding the south anchor pier.  This includes 19 approach spans, but excludes the lighting systems and their    
electrical facilities.  New Hampshire pays 100% of the cost under this project number.  
               
- 99891 includes all maintenance on the south anchor pier in New Hampshire to and including the north anchor pier in Maine.  Also included are all bearing assemblies at the anchor piers, floor expansion devices and all electrical facilities associated with the abutment to abutment. Maine and New Hampshire split the cost 50 / 50 under this project number.    
                       
- 99892 includes all  maintenance on the approach spans north of the north anchor pier to and including the north abutment in Maine.  Maine pays 100% of the cost under this project number.               
               
Total Cost is the sum of 99890 + 99891 + 99892.       
               
- Maintenance Costs include Labor, Benefits, Materials, Repair Contracts, Vehicle Usage and Upkeep, Equipment Rental and Delivery Charges.